Kickoff call
The first call ends with a question log, a source-material list and the client-side reviewers for product and legal facts.
Projects move through seven stages: brief, script, key frames, scene production, first edit, post-production and delivery. The estimate names owners, reviews, dates and files.
The first call ends with a question log, a source-material list and the client-side reviewers for product and legal facts.
The written brief becomes the approved source for the message, claims, brand restrictions and acceptance criteria.
The estimate separates work packages; the calendar shows which client input or approval releases each production step.
Key frames and the shot list show what will be filmed, modelled, generated or assembled in post-production.
Production starts after the scope, milestones, responsibilities and delivery list are accepted.
Live action, CGI and AI scenes are produced in batches from the accepted shot list. Each batch has a named review file: key frames, an animatic or a first edit.
The delivery manifest lists the master, adaptations, subtitles, sound variants, technical specifications and any source files included in handoff.
Final film and technical versions for broadcast, TV, or digital—per agreed specs.
By agreement—length cuts, subtitles, covers, and performance variants.
File structure, naming, and an acceptance checklist so marketing can ship fast.
Up to two revision rounds are included at named review points when client comments arrive as one consolidated list.
Once animation and edit logic are approved, changing shots and the shot plan is additional scope.
Production time starts when the scene list and mandatory source material are accepted. Days spent waiting for an asset or client decision are shown separately.
Before production, the producer owns scope, schedule and consolidated comments; the director signs off the script, storyboard and key frames.
Bring the current brand files, approved claims, usable footage and the people who can confirm product and legal details.
One client lead consolidates marketing, product and legal comments before sending the agreed revision batch.
Text and edit pace can still be refined after the animatic. A new shot, contributor or location requires a separate estimate.
Published guides are from 7 business days after production starts for AI video and from 20 for hybrid or classic video. Exact dates depend on the scene list and appear in the calendar.
After the brief we prepare an estimate and calendar with approval milestones; once you confirm, we lock scope in the agreement and start production.
On set, the director owns the scene and the producer owns the day. During post-production they review edit, graphics, colour, sound and master.
An unfinished brief is acceptable. Unknown parameters are labelled as assumptions in the estimate instead of being filled with invented claims or promises.
The reply lists assumptions, open questions and decisions required before the shot list and each side’s responsibility can be fixed.